The Ministry of Heavy Industries handed Letters of Intent (LoIs) to four companies under the Centre's ₹7,280-crore rare earth magnet manufacturing scheme in New Delhi on Thursday, 19 November 2026. Union Heavy Industries Minister H D Kumaraswamy gave the letters to state-run Coal India Ltd, Gurugram-based ReNew Private Ltd, Ahmedabad-based Prozeal Green Energy Ltd and Hyderabad-headquartered Midwest Energy Ltd, which were selected after an assessment of their preparedness and manufacturing capability.

The scheme targets 6,000 tonnes a year of integrated capacity for sintered rare earth permanent magnets (REPM), the powerful neodymium-iron-boron magnets used in electric vehicle traction motors, wind turbines, electronics and defence equipment.

What did the government announce?

The government picked four beneficiaries to set up integrated plants that will take rare earth oxides all the way to finished magnets. Kumaraswamy said the initiative would strengthen domestic manufacturing, cut import dependence, make supply chains more resilient and advance the Aatmanirbhar Bharat goal, according to a Press Trust of India report.

When the Union Cabinet approved the scheme on 26 November 2025, it planned to split the capacity among five beneficiaries through global competitive bidding, with each allotted up to 1,200 tonnes a year, as the Press Information Bureau release on the Cabinet decision shows. Thursday's announcement named only four recipients, and the government did not disclose how much capacity each will get.

How much money is on the table?

The total outlay is ₹7,280 crore: ₹6,450 crore in sales-linked incentives paid on magnet sales over five years, and a ₹750 crore capital subsidy for building the plants. The scheme runs for seven years from the date of award, including a two-year gestation period to set up facilities.

Business Today reported that allocations range from 600 to 1,200 tonnes a year in steps of 100 tonnes, and that the three lowest bidders will also get a limited guaranteed supply of neodymium-praseodymium (NdPr) oxide from state-run IREL (India) Ltd.

What Midwest Energy disclosed

Midwest Energy said in a statement on Friday, 20 November, that its LoI is for a 1,200-tonne-a-year plant and that it quoted a sales incentive rate of ₹505.05 per kg, The Hindu BusinessLine reported. The letter is conditional: the company must furnish a ₹40 crore performance security within 90 days, after which the government will issue a final Letter of Award once it verifies compliance.

The company said it has already invested ₹250 crore in a magnet facility in Hyderabad, whose first phase of 500 tonnes a year is being commissioned, and that it aims to reach 1,500 tonnes a year by the end of 2027. "The Letter of Intent marks an important milestone in Midwest Energy's journey towards building domestic capabilities in rare earth permanent magnet manufacturing," said Soumya Kollareddy, Whole-Time Director and Chief Executive Officer.

Why it matters

India meets its demand for these magnets mainly through imports, and the Cabinet release projects domestic consumption to double between 2025 and 2030. Business Today, citing government data, reported that between 2022 and 2025 imports from China met nearly 60-80% of India's demand by value and 85-90% by quantity.

China's export controls of April 2025 disrupted supplies to Indian electric vehicle makers, some of which had to pause production for weeks. India has estimated rare earth oxide resources of 7.23 million tonnes in monazite deposits, but large-scale manufacturing of rare earth alloys and finished magnets remains a gap in the domestic value chain.

What happens next

  • The selected companies must furnish performance security and meet the scheme's conditions to receive formal Letters of Award.
  • Award starts the two-year window to build plants, followed by five years of sales-linked incentives.
  • Capacity allocations for Coal India, ReNew and Prozeal Green Energy have not been officially disclosed.

Photo source