The Madhya Pradesh cabinet will meet at Gandhi Sagar in Mandsaur district on Wednesday, 18 November, Chief Minister Mohan Yadav said on Tuesday. The sitting is part of the state's "Destination Cabinet" series, under which cabinet meetings are held outside Bhopal. The Chief Minister told news agency ANI that this meeting is "distinct from all our previous ones".

Pumped hydro project in the spotlight

The government is using the meeting to showcase the Gandhi Sagar pumped hydro storage project. According to the ANI report carried by Free Press Journal, the plant can supply about 2,000 MW during peak demand hours. Water is moved between two reservoirs: the upper one is filled using solar power, and the stored water is released to generate electricity when demand is high.

The cost figures quoted for the project differ. Free Press Journal put it at Rs 11,474 crore, while the Chief Minister, as quoted by ANI, said the total cost is Rs 12,987 crore, calling it "essentially a Rs 13,000 crore project". An earlier report by Indian Masterminds described it as a Rs 11,500 crore, 1,920 MW project being developed by Greenko Group in Neemuch district's Rampura tehsil, with nine turbines and the existing Gandhi Sagar reservoir serving as the lower reservoir.

Mr Yadav said the foundation stone was laid during his tenure and the project is being completed during his tenure. He also said school and college science students would be brought to see the project regularly.

Tourism and fisheries pitch

The Chief Minister said the meeting is meant to draw attention to the region's development potential, tourism and jobs. He referred to the cheetah project under way at Gandhi Sagar, the area's ancient rock formations with inscriptions and prehistoric paintings, and cage-culture fish farming in the reservoir for local fishermen. He was due to visit the Manasa assembly constituency on Tuesday night to announce development works, the report said.

Rs 200 crore hamlet electrification plan may come up

Separately, Free Press Journal reported that the energy department has drafted a Rs 200 crore scheme to electrify "majra-tola" hamlets of at least 20 houses where OBC and general category families live. The proposal is expected to be placed before the cabinet at the Gandhi Sagar meeting, the newspaper said. Until now such work was limited to SC and ST settlements.

  • The scheme would be funded entirely by the state, a senior energy department officer told the newspaper.
  • A rough estimate puts the number of such hamlets at around 1,000 or more.
  • Work would be done in phases, with the aim of covering all such settlements by 2028.

Energy Minister Pradhyuman Singh Tomar did not confirm details. "Things are under consideration in this regard," he told Free Press Journal. The cabinet's agenda has not been officially released, so whether the proposal is cleared will be known only after the meeting.

What happens next

Decisions taken at Gandhi Sagar are expected to be announced after the meeting on Wednesday. Free Press Journal has also reported that the Chief Minister plans a two-day session with ministers and officers on 21 and 22 November at the Kushabhau Thakre Convention Centre in Bhopal, where departments are to present three years of work and targets for the next two years. That programme has not been officially announced.

PS · Vivek Sarje, CC BY-SA 4.0