The Madras High Court on 20 November 2026 issued notice on a public interest litigation challenging the Tamil Nadu government's decision to drop the Parandur greenfield airport, the proposed second airport for Chennai in Kancheepuram district. A first bench of Chief Justice S.A. Dharmadhikari and Justice G. Arul Murugan, sitting in Chennai, questioned how a project could be abandoned midway after land had been acquired.

Notices went to the Tamil Nadu Industrial Development Corporation Limited (TIDCO), the Union Ministry of Civil Aviation and the Airports Authority of India (AAI), PTI reported via The Federal. LiveLaw reported that the State Government was also asked to respond. The matter was posted for further hearing after four weeks.

Who filed the case, and what does it challenge?

The petition was filed by G. Gouthaman, a software consultant and book publisher, against the decision announced by Chief Minister C. Joseph Vijay in the Legislative Assembly on 24 August 2026. He wants the decision declared unconstitutional as arbitrary under Article 14 of the Constitution, which guarantees equality before law.

According to the petition as reported by LiveLaw, the project was valued at ₹27,400 crore, more than ₹680 crore of public money had already been spent and over 1,700 acres had been acquired across several villages. The petitioner argues that no technical data, expert committee report or comparative economic study was placed before the Assembly to justify dropping it.

He has asked the court to direct the authorities to reconsider the project through a reasoned decision based on official records and updated expert inputs, including from AAI. The Federal reported that the plea also seeks production of internal files, hydrogeological reports and feasibility documents, and a stay on the 24 August decision.

What did the court say?

During the hearing, the bench orally remarked that "airports can't be constructed on your whims and fancies", according to LiveLaw. It said feasibility factors should have been weighed before the site was approved.

Advocate General Vijay Narayan told the court that the state dropped the project because much of the land acquired was water bodies or farmland and environmental clearance would be difficult to obtain. The bench responded that these issues should have been examined in the earlier feasibility study.

How was Parandur chosen?

The petition, as cited by The Federal, says a government order dated 31 October 2023 sanctioned the acquisition and transfer of land in Parandur and 19 other villages in Kancheepuram and Sriperumbudur taluks in favour of TIDCO. Parandur was picked over Pannur, Thiruporur and Padalam after feasibility studies by AAI and TIDCO, which cited its closeness to the Chennai–Bengaluru Expressway, fewer airspace obstacles, lower land costs and room to expand.

A high-level committee chaired by a retired IAS officer, with experts from IIT Madras and Anna University, was set up to carry out hydrological studies so that new water storage would exceed any storage affected by the project, the petition says.

Why it matters

The outcome of the case will decide whether land already acquired and money already spent at Parandur are written off. The court has not stayed the government's decision; it has only sought responses.

What next

TIDCO, the Civil Aviation Ministry and AAI are expected to file their replies before the next hearing, due after four weeks. Whether the state has an alternative site in mind was not part of the reported proceedings.

Photo source · Kalyan07kumar, CC BY-SA 4.0