The Indian Navy took delivery of DSC A21, a home-built diving support craft, at the Naval Dockyard in Mumbai on 20 November 2026, the Ministry of Defence said. The vessel was designed and built by Titagarh Rail Systems Limited (TRSL) of Kolkata, according to the ministry's release.

DSC A21, built as Yard 326, is part of a five-ship Diving Support Craft project that the Navy ordered to strengthen its diving and underwater work in harbours and along the coast.

What is a diving support craft used for?

It is a small specialist ship that carries divers and their equipment to where they are needed and supports them while they work underwater. The Ministry of Defence said the induction of these craft will boost the Navy's capabilities in diving support, underwater inspection, salvage assistance and coastal operational deployment.

When the first ship of the class was launched in 2023, the ministry said the craft were designed for operational and training diving in harbours and coastal waters, and described them as 30-metre catamaran-hull ships displacing about 300 tonnes, according to a PIB release from 31 August 2023.

What makes DSC A21's design different?

The ship uses a catamaran hull, with two parallel hulls instead of one. The ministry said this gives it better stability, a larger deck area and improved sea-keeping, which suit its specialist role. It is fitted with what the ministry called state-of-the-art diving equipment.

The vessel was built under the naval rules and regulations of the Indian Register of Shipping (IRS), the national classification society. Hydrodynamic analysis and model testing during the design stage were carried out by the Naval Science and Technological Laboratory (NSTL) in Visakhapatnam, the ministry said.

How far along is the five-ship project?

The contract for the five craft was signed between the Ministry of Defence and Titagarh Wagons Ltd, as the company was then known, on 12 February 2021, the 2023 release said. The first ship, DSC A20 (Yard 325), was launched on the Hooghly River at Titagarh near Kolkata on 31 August 2023, and the keel of the fifth and last craft, DSC A24, was laid the same day.

That 2023 release had said all five craft were expected to be delivered in the 2024-25 financial year. The programme has run past that target: DSC A24 was launched at Titagarh only on 1 August 2026, All India Radio News reported at the time, citing the Ministry of Defence. The 20 November release did not say when the remaining craft will be handed over.

Why does it matter?

The ministry described DSC A21 as a flag-bearer of the government's Make in India initiative. At the time of the DSC A24 launch, the ministry said about 70% of the main and auxiliary equipment on these craft is sourced from Indian manufacturers, according to All India Radio News.

The project is also an example of a company better known for railway wagons and coaches building warships for the Navy. Coastal diving tasks such as hull inspections, harbour clearance and salvage support are routine but essential work for a navy, and dedicated craft let these jobs be done without tying up larger warships.

What happens next?

After delivery, a ship is normally inducted into service by the Navy, but the ministry has not announced a date for DSC A21's commissioning. Further deliveries under the five-ship project are expected, though no timeline has been given.