Google has paused construction of an artificial intelligence (AI) data centre at Farciennes in Belgium's Wallonia region "pending additional guidance", the company said in a statement reported on 29 November 2026, after regional authorities described the works as "illegal construction" carried out without a valid planning permit. The halt order from the Walloon government was issued on Thursday, 26 November, for the site near Charleroi that spans Farciennes and Aiseau-Presles, according to tech news outlet The Next Web.
Wallonia government spokesperson Nicolas Yernaux called the lack of the correct permit a "major offence", BBC News reported. Around 300 construction workers were on site when the order was issued, The Next Web said, citing Walloon official Raphael Stokis speaking to Belgian broadcaster VRT.
Why was the construction declared illegal?
The dispute centres on a permit Google no longer holds. According to The Next Web, Google's original 2024 permit covered three air-cooled data centres. In 2025 the company merged two of the buildings into one larger structure and switched to a cooling system drawing water from the River Sambre. The Walloon administration approved the amended permit in April 2026, but after residents appealed, regional minister François Desquesnes revoked it in August.
The amended plan sought up to 600 cubic metres of river water an hour, with less than a quarter to be returned to the river, according to the Belgian news agency Belga as cited by The Next Web. Work on the site nevertheless continued after the revocation, prompting complaints from residents and environmental groups, BBC News reported. Mr. Desquesnes announced an investigation on 25 November.
What has Google said?
In its statement, Google said: "We have operated in Belgium for over 15 years and remain committed to complying with local laws." A company spokesperson also said Google is committed to open and collaborative dialogue with the regional government and experts about its investments in Wallonia, according to The Next Web.
Google has challenged the revocation. On 17 October 2026 it asked Belgium's Council of State, the country's highest administrative court, to annul and suspend the minister's decision, The Next Web reported. Greenpeace Belgium and several residents asked to join the case on 16 November.
Environmental groups react
Greenpeace Belgium said it used satellite imagery to check reports from residents that building had carried on, and launched an emergency procedure earlier in the week. "That Google continues to build without a permit is disrespectful to the environment, local residents, and the law," Joeri Thijs of Greenpeace Belgium told the BBC. Greenpeace spokesperson Nadia Cornejo said action should have come in August, when the permit was cancelled.
Why it matters
The Farciennes case adds to a growing backlash in Europe and the United States against the large data centres powering the AI boom, driven largely by concerns over how much energy and water they consume. Around 13,500 data centres operate worldwide, 54 of them in Belgium, according to the tracker Data Center Map, as cited by the BBC.
What happens next?
A public hearing in the Council of State case is scheduled for 7 January 2027, according to The Next Web. Until then, the site remains paused while Google consults the regional authorities. It is not yet confirmed whether any work allowed under the original 2024 air-cooled permit can resume.
Photo source · Carl Lender, CC BY 2.0