Chief Justice of India Surya Kant on Monday, 23 November 2026, stepped away from hearing the Supreme Court case on the completion of 16 stalled housing projects of Supertech Limited, saying one of the many applicants in the matter was known to him. The case, heard in New Delhi by a bench that also included Justice Joymalya Bagchi and Justice V Mohana, will now go to a specially constituted bench.
Why did the Chief Justice step aside?
The Chief Justice recused himself because one of the applicants who had joined the proceedings is personally known to him, according to courtroom reports by LawChakra, Law Trend and The Hans India. "One of the applicants is incidentally known to me. I will not hear," he said, according to LawChakra. Reports said the person was neither a relative nor a former client.
The Chief Justice also questioned why that individual had become a party at all, noting that hundreds of applications had already been filed in the matter. "Somebody should have realized this…why unnecessarily become a party?" he remarked, as reported by LawChakra. No order was passed on the merits of the case on Monday.
What is the Supertech case about?
The dispute arises from the insolvency of Supertech Limited, a real estate developer. According to Law Trend's report on the hearing, the National Company Law Tribunal (NCLT) admitted an insolvency application filed by Union Bank of India against the company on 25 March 2022. The National Company Law Appellate Tribunal (NCLAT) later directed that the 16 unfinished projects be completed through the government-owned NBCC (India) Limited, the report said. The case is listed as Apex Heights Pvt. Ltd. v. Ram Kishor Arora & Anr.
The Hans India reported that the projects account for nearly 50,000 homes spread across Uttar Pradesh, Haryana, Uttarakhand and Karnataka, and that construction is being supervised by an Apex Court Committee headed by former Supreme Court judge Justice (retd) Krishna Murari. Some buyers have waited more than two decades for possession, according to Law Trend.
Homebuyers' concerns before the court
Homebuyers, their associations and other stakeholders have filed a large number of applications in the Supreme Court. The Hans India reported that homebuyers have objected to more than ₹30 crore reportedly being spent on appointing NBCC as project management consultant without a tender. In May, the NCLAT rejected NBCC's request for an exemption from real estate regulator (RERA) requirements and its demand for higher fees from the sale of unfinished flats, the paper reported, adding that NBCC's plea on the RERA exemption is also pending in the Supreme Court.
The court has also considered whether the supervising committee should be replaced by a court-appointed receiver, as was done in the Amrapali and Unitech housing cases, according to The Hans India. The bench has indicated that homebuyers should not face extra financial burdens and has pointed to unsold flats and vacant plots as possible sources of funds, the report said.
Why it matters and what happens next
The recusal means the long-running matter, which affects tens of thousands of families waiting for homes, will be heard by a fresh bench rather than by the Chief Justice's bench that has been handling it. The Chief Justice indicated that the special bench would be constituted promptly, but the bench's composition and the next date of hearing had not been officially announced at the time of writing. Pending questions over how the project-completion arrangement should be implemented and funded will be taken up by the new bench.
Earlier this month, MapMyTimes reported on another homebuyers' case in which the Supreme Court shielded Gurugram homebuyers from SBI instalment demands.
Photo source · Pinakpani, CC BY-SA 4.0