Madhya Pradesh Chief Minister Mohan Yadav on 23 November 2026 chaired the seventh meeting of the state's cabinet committee for Simhastha 2028 at Mantralaya in Bhopal, where the committee approved 33 works worth ₹2,801.75 crore for the mass religious gathering in Ujjain, according to reports of the meeting by Mediawala and the Free Press Journal.

The Chief Minister directed that all Simhastha works now under construction or already sanctioned must be finished by the end of 2027, and said the committee will meet every month to review progress.

What did the Simhastha committee approve?

The committee cleared 33 works recommended by a supervision committee: 16 works worth ₹1,457.04 crore from its ninth meeting and 17 works worth ₹1,344.71 crore from its tenth meeting, Mediawala reported. The largest items listed include:

  • Power: a ₹387.99 crore temporary plan from the Energy Department, with five temporary 33/11 kV substations, about 1,000 distribution transformer structures, 250 generators and roughly 4,500 connections for camps of saints and institutions.
  • Police equipment: ₹207.61 crore for bomb detection and disposal squad (BDDS) equipment, ₹207.33 crore for security equipment, ₹220.06 crore for traffic and crowd-control equipment and ₹199.34 crore for vehicles. About 100 BDDS teams are expected to be needed.
  • Roads and parking: 122 km of temporary roads for ₹34.82 crore, 17 km of temporary pathways to the ghats for ₹32.34 crore, and ₹112.34 crore to develop parking and service areas.
  • Transport: ₹45 crore for the Ujjain Development Authority to run 2,000 buses between ghats, akharas, parking lots and transport hubs.
  • Health and fire safety: ₹27.78 crore for medical services in the fair area and ₹18.23 crore for firefighting.

More guards, volunteers and a visitor centre

The committee approved ₹155.08 crore from the State Disaster Management Fund for home guards, civil defence and disaster management. Home guard strength is to rise to 11,500 from 8,000 at Simhastha 2016, and civil defence volunteers to 10,000 from 4,000, according to Mediawala.

Other approvals include ₹120.38 crore for administrative tents, including dormitories for 40,000 people; ₹25.15 crore to train vendors, hotel staff and auto-rickshaw drivers; ₹100 crore to upgrade 147 city junctions; and ₹90 crore for a "Simhastha Experience Centre" of about 75,000 sq ft, to be built on a public-private partnership model with augmented and virtual reality zones.

Drone surveillance and anti-drone technology have also been proposed for Ujjain, Omkareshwar, Maheshwar, other religious sites and inter-state borders, the report said.

Why does the 2027 deadline matter?

It leaves the state roughly a year before the 2028 event to test roads, power and crowd systems. The Chief Minister said there should be no shortfall in managing Simhastha 2028 and asked officials to build permanent paths to all ghats of the Kshipra river. He also asked that the event be organised on a "Clean and Green Simhastha" theme focused on sanitation, environmental protection and better facilities for pilgrims.

The Free Press Journal reported that the Ujjain Municipal Corporation's proposals included ₹393.53 crore for toilets and bathing facilities and their upkeep, with public toilets planned every 500 metres.

Who attended?

Deputy Chief Minister Rajendra Shukla, Water Resources Minister Tulsi Silawat, Food and Civil Supplies Minister Govind Singh Rajput, School Education and Transport Minister Uday Pratap Singh, MSME Minister Chetanya Kashyap, Minister of State for Urban Development Pratima Bagri and Chief Secretary Ashok Barnwal were among those present, Mediawala reported.

The approvals came on the same day as a separate Madhya Pradesh cabinet meeting that cleared over ₹7,000 crore in proposals, including Advaita Lok in Omkareshwar. The Simhastha committee is next due to review progress at its monthly meeting.

Photo source · Bernard Gagnon, CC BY-SA 3.0