The overhead power system on the roughly 50-km Surat–Bilimora section of the 508-km Mumbai–Ahmedabad bullet train corridor in Gujarat has been switched on, the Ministry of Railways said on 21 November 2026. The overhead equipment (OHE) on both the Up and Down lines of the elevated stretch was energised on 20 November, according to an ANI report carried by The Tribune.
Does this mean bullet trains will start running on the stretch?
No, not yet. Officials said energisation does not mean the section is ready for train operations, though it is a significant step towards that goal, the Press Trust of India reported from New Delhi. ANI reported that the step moves the project closer to further testing.
What has been energised?
The corridor uses a 2 × 25 kV overhead traction system. Along the full 508-km route, 14 traction substations will draw electricity from the national grid, and a centralised control centre will monitor the network, according to the ministry's details reported by PTI and ANI.
The first traction substation, at Bilimora in Navsari district, has completed installation of its control panel, changeover switch, transformer and circuit breaker buildings, ANI reported. It draws power from the 220 kV Ambetha grid substation operated by the Gujarat Energy Transmission Corporation (GETCO).
The Surat–Bilimora section runs on an elevated alignment of about 50 km, with bridges across four rivers and a steel bridge over National Highway 53. About 94,000 noise barriers have been fitted along the viaduct.
What safety warning has the ministry issued?
The ministry said energisation will be carried out progressively in smaller sections under close supervision of technical teams to ensure safety and compliance with procedures. It issued a public advisory cautioning residents, commuters, construction workers and others living or working near the alignment not to approach or touch the overhead installations, and not to carry out unauthorised work close to them now that the system has been energised.
When will passengers be able to ride?
Railway Minister Ashwini Vaishnaw said on 20 November that India's first bullet train service will start in 2027 on the Surat–Vapi stretch, as MapMyTimes reported. PTI noted that the ministry had recently pushed the deadline for starting operations on the 100-km Surat–Vapi section from August 2027 to the last quarter of 2027.
Why it matters
The Mumbai–Ahmedabad line is India's first high-speed rail project. With civil structures such as the viaduct, river bridges and noise barriers in place, switching on traction power on the Surat–Bilimora stretch takes the project into its electrical systems stage there, though officials stress that it is not yet ready for trains to run.