Jaipur-based RMC Switchgears Limited said on Monday, 23 November 2026, that it has received Letters of Award worth ₹521.84 crore (₹521,83,68,000) for power distribution infrastructure work, according to a disclosure filed with the National Stock Exchange of India and BSE.
The company has not named the customer. In its filing under Regulation 30 of the Securities and Exchange Board of India's listing rules, it said the identity of the awarding entity is "confidential (due to commercial confidentiality)", while describing the customer as a domestic entity.
What does the order cover?
The order covers what the company calls development of distribution infrastructure and systems strengthening. The scope includes supply, testing, transport, construction, erection and commissioning of new substations, augmentation of existing substations, additional power transformers, high-tension (HT) lines and other allied works, along with supply and works guarantees.
The filing classifies the contract as civil work plus supply and installation of plant and equipment. It is to be executed within 24 months.
Is anyone related to the company involved?
No, according to the company. RMC Switchgears said its promoter, promoter group and group companies have no interest in the entity that awarded the order, and that the contract does not fall within related-party transactions.
Why does it matter?
The company said the award "further strengthens the Company's order book and is expected to contribute positively to the Company's revenue and growth prospects". The disclosure was signed by Company Secretary and Compliance Officer Shivani Bairathi on the evening of 23 November, and the company said it will update the exchanges on further material developments.
The order adds to a run of power-sector contract announcements by listed Indian companies on the same day, including Sterling and Wilson Renewable Energy's orders worth more than ₹2,050 crore, reported by MapMyTimes.
What is still unknown?
The filing does not identify the state or utility where the substations and lines will be built, the number of substations involved, or the payment terms. It also does not say whether the amount includes Goods and Services Tax. These details have not been made public by the company.
What happens next?
RMC Switchgears, whose registered office and factory are in Badodiya village in Kotkhawada tehsil of Jaipur district, Rajasthan, will now have to execute the work over the next two years. Investors will be able to see the market's response when trading opens on 24 November, since the filing came in the evening of 23 November.
Photo source · Aliva Sahoo, CC BY-SA 4.0