The National Green Tribunal (NGT) Central Zone Bench in Bhopal ordered the Bhopal Municipal Corporation (BMC) on November 27 to immediately demolish a 50-metre temporary earth road built inside Shahpura Lake's wetland zone and dispose of excavated debris outside a 50-metre buffer or at designated landfills.

Tribunal Rebukes Authorities Over Missing Reports

A bench comprising judicial member Justice Shiv Kumar Singh and expert member Dr Prashant Gargava issued the directives while hearing an application filed by Nitin Saxena against the Madhya Pradesh State Wetland Authority. The tribunal expressed dissatisfaction over the failure of the Madhya Pradesh Pollution Control Board (MPPCB), State Wetland Authority, and BMC to file action taken reports on its September 2 order, setting December 8 as the next hearing date.

Joint committee findings also flagged suspected encroachments involving the MPPCB office building and a nearby government school near Shahpura Lake. The Bhopal District Collector and State Wetland Authority were given one week to carry out measurements and report action, while the area Sub-Divisional Magistrate must submit a personal affidavit certifying that no encroachments or untreated sewage exist within 33 metres of the Full Tank Level.

Four-Month Statewide Wetland Mapping Directive

Applying Supreme Court directions issued on October 12, 2026, the NGT ordered the Chief Secretary, Environment Department Principal Secretary, and State Wetland Authority to submit a compliance affidavit within four weeks and complete scientific wetland demarcation across Madhya Pradesh within four months.

Authorities must follow Tamil Nadu's four-stage framework pairing satellite imagery and GIS mapping against digitised village cadastral records, field verification by revenue teams, and differential GPS demarcation, alongside installing permanent boundary pillars, fencing, and dense plantation around water bodies smaller than 2.25 hectares.