The long-awaited Tihi–Dhar railway line in Madhya Pradesh has received permission for train operations following an inspection by the Commissioner of Railway Safety (CRS), the Free Press Journal reported on Monday, 16 November. The clearance brings Dhar, a tribal-majority district headquarters that has never had a rail link to Indore, a step closer to its first train.
What has been cleared
According to the Free Press Journal, the line was cleared for running trains after the CRS inspection. The report did not give the date of the clearance order, any conditions attached to it, or a date for the start of passenger services.
The section is part of the 204.76-km Indore–Dahod new line connecting Madhya Pradesh and Gujarat. Swarajya reported on 8 November that the CRS for the Western Circle, E Srinivas, inspected the 44-km Tihi–Dhar stretch on 5 and 6 November, checking the track, signalling, electrification and the roughly 3-km Tihi tunnel. Trial trains touched 120 kmph during the inspection, it said.
Minister credits Centre and state
Savitri Thakur, the Union Minister of State for Women and Child Development and the MP for Dhar, thanked Prime Minister Narendra Modi, Railway Minister Ashwini Vaishnaw and Chief Minister Mohan Yadav after the clearance, the Free Press Journal reported. She said the Centre's focus on railway modernisation was benefiting the Dhar region and expressed confidence that expanded rail services would speed up development in the constituency.
The newspaper said the line is expected to help industry, trade, employment and tourism in the district, and in particular to improve connectivity for workers and businesses in the Pithampur industrial area.
A project sanctioned in 2008
The Indore–Dahod line was sanctioned in 2008 and construction began in 2013, according to Swarajya. Once trains run, Dhar district will have direct rail connectivity with Indore for the first time since Independence, it reported. The section has 25 kV overhead electrification and ballastless track inside the tunnel.
What happens next
Swarajya had reported after the inspection that the CRS found drainage at some bridges needed improvement and bridge bearings needed replacing at certain sites, and that these had to be addressed before passenger services could begin. It is not clear from Monday's report whether that work has been completed.
The same report said passenger services were expected in late November or December 2026, subject to corrective work and final clearances, with MEMU trains likely to be the main service between Indore and Dhar. The railways have not announced a timetable or an inauguration date.