The Calcutta High Court has deferred the final hearing on a batch of public interest litigations challenging clearances for the ₹92,000-crore Great Nicobar Island infrastructure project to January 13, 2027, after the Union Government requested additional time to file affidavits addressing tribal rights and forest diversion.

Dispute Over Forest Rights Act Applicability

Appearing before a Bench led by Chief Justice Ravindra Vithalrao Ghuge, Attorney General R. Venkataramani and Additional Solicitor General Vikramjit Banerjee sought leave to clarify the legal status of indigenous forest protections in the Andaman and Nicobar Islands. Central counsel argued that the Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 (FRA) has not been implemented in the archipelago because tribal protections remain governed by the Andaman and Nicobar Islands (Protection of Aboriginal Tribes) Regulations, 1956.

Petitioners challenging the diversion of 121 square kilometres of tropical rainforest countered that the Andaman and Nicobar administration had itself issued a compliance certificate under the 2006 Act while processing clearances for the mega transshipment port, airport, township, and power project.

Ecological Clearances and Next Court Timelines

Alongside tribal consent questions, the writ petitions challenge reductions made to buffer zones surrounding two notified national parks on Great Nicobar Island. Environmental and legal petitioners contend that the project's scale threatens sensitive coastal and terrestrial ecosystems home to particularly vulnerable tribal groups.

Directing the Union Government to submit its additional affidavits within 10 days, the High Court scheduled the next final hearing for January 13, 2027, and allotted January 22, 2027 for submissions by the Attorney General.