The Supreme Court on Tuesday, 17 November 2026, took up the matter of Bhopal's Adampur waste processing site and expressed satisfaction with the progress made by the Bhopal Municipal Corporation (BMC) in clearing old, accumulated garbage, the Free Press Journal reported. According to the report, 2,64,577 tonnes of legacy waste have been processed at the site so far.
What the court said, as reported
The newspaper reported that the court was satisfied with the efforts made and the material placed before it, and that it commended the civic body for the pace and direction of the work. The court was also satisfied with the action plan the corporation has drawn up to meet its processing targets, the report said.
The report did not name the judges on the bench, set out any specific directions or give the next date of hearing. The court's written order was not available at the time of writing, so the account of the hearing rests on the newspaper's report.
How the pace picked up
The Free Press Journal attributed the faster processing to close monitoring by Municipal Commissioner Ramprakash Ahirwar, who has been holding weekly reviews and inspecting the dump site. During those inspections he ordered additional machinery to be deployed, the report said.
Equipment now working at Adampur includes high-capacity shredders along with other processing machines, according to the report. The commissioner is also reviewing every day how much refuse-derived fuel, the combustible fraction recovered from old waste, can be sent out for disposal.
How much is left
Legacy waste is garbage that has been lying in dumps for years. It is cleared through bio-mining, in which the heap is dug up and sorted into soil-like material, recyclables and fuel.
In June 2026 the Free Press Journal, citing Urban Administration Department records, reported that about 7.5 lakh tonnes of legacy waste lay at Adampur and that only about 95,000 tonnes had been processed until then. It described the site as Bhopal's biggest waste challenge. A fresh official estimate of the remaining quantity was not part of Tuesday's report.
The same June report quoted Swachh Bharat Mission managing director Shishir Gemawat as saying that pending legacy waste disposal in the state would be completed by December.
What happens next
The corporation maintains that remediation of the Adampur dump will be finished within the stipulated time frame, the Free Press Journal reported, without giving the date. The matter remains before the Supreme Court.