Trial runs have commenced on the Phase 2A stretch of Bengaluru's Namma Metro Blue Line from K.R. Puram across the first four stations along Outer Ring Road, with public passenger services targeted to open by the middle of 2027, Greater Bengaluru Development Minister Krishna Byre Gowda said after inspecting the corridor on November 24, 2026.

Testing Schedule and Outer Ring Road Connectivity

Testing is currently underway across the first four stations toward Mahadevapura and will be expanded by another four stations next month. Automatic signalling installation is scheduled for completion by January 2027, followed by mandatory safety certification starting after February—a process officials estimate will take seven to eight months before commercial services open.

The 19-km Phase 2A corridor between K.R. Puram and Central Silk Board comprises 13 stations and runs through Bengaluru's Outer Ring Road (ORR) employment belt, which serves an estimated 11 lakh to 12 lakh daily commuters working across major technology and business parks.

Full Airport Corridor Progress and BMRCL Finances

Phase 2A forms part of the wider 58.2-km Blue Line project linking Central Silk Board through K.R. Puram and Hebbal to Kempegowda International Airport at an estimated cost of around ₹20,000 crore. State authorities have directed Bangalore Metro Rail Corporation Limited (BMRCL) and contractors to accelerate civil works on the Phase 2B K.R. Puram–Hebbal–Airport stretch, targeting completion of the full corridor within 18 months.

Addressing project financing, Mr. Gowda noted that exchange-rate fluctuations and approval delays have raised costs and loan repayment pressures. While BMRCL records an operating surplus of ₹50 crore to ₹60 crore excluding depreciation, its annual loss including depreciation stands at ₹600 crore to ₹700 crore; however, the government has taken no decision to raise metro fares.