Belgian authorities in the Wallonia region ordered Google to halt construction on a nearly completed artificial intelligence data centre in Aiseau-Presles, near Charleroi, after discovering around 300 workers were continuing work on the three-hectare structure despite the revocation of its amended planning permit in August 2026.
Why Wallonia Issued a Stop-Work Order
Walloon officials issued verbal and written notices late on November 26 and November 27 following an emergency complaint from Greenpeace Belgium supported by drone and satellite imagery recorded between August and November 2026. Wallonia spokesperson Nicolas Yernaux described the ongoing assembly of the massive building as a major planning offence, and regional official Raphaël Stokis confirmed prosecutors had been alerted.
In response, Google stated on Saturday, November 28 that it had paused operations at the 50-hectare Écopole site pending further regulatory guidance while maintaining its commitment to Belgian laws.
River Sambre Water Cooling Dispute and Legal Timeline
- Permit amendment clash: Google won initial approval in 2024 for three smaller air-cooled data centres, but submitted a 2025 revision merging two buildings and shifting to water cooling drawing roughly 600 cubic metres per hour from the nearby River Sambre.
- Drought revocation: Although the regional administration approved the update in April 2026, Walloon Environment and Infrastructure Minister François Desquesnes revoked it in August 2026 after residents and environmentalists warned about severe droughts straining local waterways.
- Court appeal pending: Google challenged the permit revocation before Belgium's Council of State in October 2026, with a public hearing scheduled for January 7, 2027.
AI Boom Versus Water Scarcity in Europe
The confrontation underscores growing tension across Europe as hyperscale technology firms race to build high-capacity AI computing clusters while regional governments enforce tighter limits on industrial electricity and freshwater consumption.