Solar module maker Vikram Solar reported a steep fall in quarterly profit on Saturday, with net profit for the September quarter shrinking about 95 per cent as costs rose and sales slipped. The company said the weaker volumes were a temporary dip and pointed to a stronger order intake and progress on its new cell factory in Tamil Nadu.
According to the consolidated results for the quarter ended 30 September 2026 (Q2 FY27), filed on 14 November, net profit came in at about ₹5.93 crore, compared with about ₹128.5 crore in the same quarter a year earlier. Revenue from operations was about ₹1,077 crore, slightly lower than a year ago.
Costs squeeze earnings
Total expenses for the quarter reached about ₹1,084.7 crore, nearly matching revenue, and profit before tax shrank to roughly ₹6.6 crore from about ₹184.5 crore a year earlier, reports on the filing showed. Operating profit fell by more than half compared with the same quarter last year, and the net profit margin fell to well under 1 per cent. Profit was also lower than in the April–June quarter, when the company earned about ₹18.7 crore.
For the first half of the financial year, however, the company said revenue from operations was 17.7 per cent higher than in the first half of FY26.
What the company says
In its results statement, Vikram Solar said its absolute EBITDA per watt improved by about 37 per cent over the previous quarter despite lower volumes. The share of modules sold under the domestic content requirement (DCR), which applies to solar projects that must use Indian-made cells, rose to 22 per cent from 7.5 per cent in Q1. Distribution and retail sales rose to 44 per cent of volumes from 14 per cent.
The company booked about 1.7 GW of new orders during the quarter, more than double the 0.8 GW it won in the first quarter. Its net debt-to-equity ratio stood at 0.17 times at the end of September.
"Q2 FY27 was a period in which we strengthened the foundations of the business," Chairman and Managing Director Gyanesh Chaudhary said, adding that the company "will measure progress through execution and cash generation."
Cell plant and battery storage plans
Vikram Solar said its 9 GW N-type TOPCon solar cell facility at Gangaikondan in Tamil Nadu is expected to produce its first cells in December 2026, with full capacity to be commissioned in phases after that. It plans a 9 GW ingot and wafer facility at the same site by FY29, which would give it a supply chain running from wafers to cells to modules.
Through its wholly owned subsidiary VSL PowerHive, the company is also setting up a battery energy storage system assembly plant at Oragadam near Chennai with a capacity of 7.5 GWh a year, which can be scaled up to 15 GWh. The company said the plant is slated to be inaugurated in January 2027 and begin commercial operations in April 2027, with 7.5 GWh of battery cell manufacturing planned from 2028.
Why it matters
India's solar manufacturers have been expanding rapidly to meet demand from the country's renewable energy push and government rules favouring locally made equipment. Making cells, rather than only assembling imported cells into modules, is central to that shift, since DCR projects require Indian-made cells. Vikram Solar's results show the pressure on module makers' earnings during this transition, even as their order books grow.
What happens next
The company said its focus for the second half of FY27 is on converting orders into sales, using its factories more fully, growing DCR volumes and commissioning the cell project. Investors will watch whether the Tamil Nadu cell line starts on schedule in December, and whether volumes recover in the coming quarters.