The estimated cost of the Kopra Medium Irrigation Project in Madhya Pradesh's Sagar district has more than tripled from Rs 292.38 crore to Rs 957.16 crore after statutory wildlife protections sharply raised forest and land compensation charges. Originally sanctioned on October 4, 2018 as a major irrigation initiative in Rehli MLA Gopal Bhargava's constituency, the project aims to provide irrigation across 9,990 hectares.
Tiger Reserve Notification Triggers Tenfold Forest Charges
Officials attributed the steep cost escalation primarily to the 2023 notification of the former Nauradehi Sanctuary as the Veerangana Durgavati Tiger Reserve. Under the revised boundary, about 268.39 hectares of submergence-affected forest land fell inside the reserve's core area, activating statutory norms requiring ten times the standard Net Present Value and compensatory payments.
As a result, forest department compensation alone rose to roughly Rs 400 crore alongside increased private land acquisition rates. A gazette notification dated November 6, 2026 documented compensation liabilities impacting 897 families across 13 villages in the project zone.
State Pushes for Ken-Betwa Link Central Funding
With capital costs crossing Rs 957 crore, the Madhya Pradesh Water Resources Minister has written to the Union Ministry of Jal Shakti requesting the Kopra scheme's inclusion under the Ken-Betwa Link National Project.
If approved as part of the national river-interlinking framework, 90 percent of the project expenditure would be funded by the Centre, reducing the Madhya Pradesh government's financial burden to roughly Rs 95 crore and helping revive construction progress in Sagar's Bundelkhand belt.