The Odisha cabinet approved the cost and implementation framework for the 600 MW Upper Indravati Pumped Storage Project on November 9, 2026. The project at Ranibahal in Kalahandi district has an estimated total cost of ₹4,708.64 crore and is targeted for commissioning in financial year 2030–31.

The decision was taken at a meeting chaired by Chief Minister Mohan Charan Majhi. Chief Secretary Anu Garg briefed reporters on the approval, according to PTI. UNI independently reported the cost, capacity and financing arrangement.

Storage linked to the existing reservoir

The Odisha Hydro Power Corporation’s project description says the scheme will be built beside the existing Upper Indravati hydroelectric project. It will use the Indravati reservoir as its upper reservoir, with a new lower reservoir and an underground powerhouse.

The planned generating capacity is four units of 150 MW each. OHPC estimates annual generation at 1,040 million units and annual energy used for pumping at 1,283 million units.

Those figures illustrate the project’s storage role: electricity is used to pump water uphill when demand is lower, and the stored water is released to generate electricity when it is needed. Pumped storage shifts energy between periods rather than creating electricity without an energy input.

Financing and implementation

The approved framework envisages an 80:20 debt-equity ratio. OHPC is to contribute the equity in phases from internal reserves, with the state government providing the remaining financing as phased loans. Megha Engineering & Infrastructures has been selected as the engineering, procurement and construction contractor, according to the cabinet briefing reports.

The 2030–31 commissioning date is a target. Approval of a financial and construction framework does not mean the new facility has started supplying power.

Earlier technical clearances

OHPC’s project page lists techno-economic clearance from the Central Electricity Authority in August 2024 and further state-level approvals in 2024 and April 2025. The November 9 cabinet decision therefore advances an existing proposal rather than marking its first conception.

The project is intended to support peak-demand supply and grid operations. Its eventual contribution will depend on construction, commissioning and the availability of electricity for pumping.