Indore's new Inter-State Bus Terminal (ISBT) at Kumedi, near MR-10, is still not handling a single scheduled bus. More than ₹100 crore has gone into the facility, and a trial run was held about two weeks ago, but its gates remain locked, the Free Press Journal reported on 14 November 2026.

A Regional Transport Office (RTO) official, Pradeep Sharma, confirmed that bus services from the terminal have not begun. He said the contractor had not completed the arrangements required to run it.

A long road to operations

The terminal was built by the Indore Development Authority (IDA) to organise intercity bus movement and give passengers modern facilities. Running it was first handed to Atal Indore City Transport Services Limited (AICTSL), and bus services were announced. AICTSL could not make the operation work and passed the job to a private contractor.

The IDA had to invite tenders three times before it picked a firm, took the required security deposit and signed an agreement. It later announced a trial run through a press release. That trial, held with the RTO's help, remained incomplete and did not lead to regular services, the report said.

In August 2026, BVG India said it had won a long-term lease-cum-operation and maintenance contract for the Kumedi ISBT, according to a report in The Machine Maker. Under that contract the company is to manage engineering systems, passenger amenities, parking, traffic movement, safety and day-to-day operations of the terminal.

What the terminal offers

According to the Free Press Journal, the terminal is designed for around 80,000 passengers a day and has space for parking about 1,200 buses. It has CCTV surveillance, parking, nearly three dozen shops and four large restaurants, and it connects to the nearby metro station so passengers can continue their journey by metro. BVG's description of the project, as reported by The Machine Maker, gives somewhat different figures: a 5.85-hectare site, capacity for more than 1,500 buses and roughly 50,000 to 55,000 passengers and visitors a day, with a foot overbridge to the metro station and planning for crowds during Simhastha 2028.

What still has to happen

Sharma said that, besides the contractor finishing its work, a detailed plan has to be drawn up with the traffic police so that buses can move in and out without jamming the roads around the terminal. The IDA says it is pressing the contractor to complete the pending work so that operations can start soon. No date for the first scheduled departures has been announced.

Until then, a facility meant to ease intercity travel for one of Madhya Pradesh's busiest cities stays shut, and commuters continue to rely on the city's existing bus stands.