A division bench of the Madhya Pradesh High Court in Gwalior has given four parties two weeks to put forward a concrete plan for cleaning up the Swarna Rekha river, after drone footage shown in court revealed construction debris, garbage and 84 drains emptying into it, Dainik Bhaskar reported.

The bench watched the drone video during a hearing on Tuesday, 17 November. The footage covered a 13-kilometre stretch of the river from Hanuman Bandh to Jalalpur, according to the newspaper.

Elevated road debris the main obstruction

The hearing brought out that the biggest blockage in the river is not household waste but rubble from the construction of the elevated road, the report said. The court remarked that the river cannot be kept clean without a joint effort by administrative officers and citizens.

Pointed questions to each department

After viewing the footage, which was presented by the Gwalior Municipal Corporation, the bench put separate questions to each side:

  • Water Resources Department (WRD): why it had failed completely in maintaining the river despite being responsible for its upkeep.
  • Public Works Department (PWD): by when debris would be cleared from the stretches of the elevated road where work is complete, and what the timeline is for the remaining construction.
  • Municipal corporation: on what permission the 84 drains flow into the river, and how effective the city's door-to-door garbage collection really is.

Civic body's response

The corporation told the court that people dump rubbish into the river late at night or early in the morning, making it hard to identify them. In its compliance report it said it had so far collected Rs 16,000 in fines from those caught throwing waste, and that awareness drives are being run in settlements along the riverbank, Dainik Bhaskar reported.

Lawyers asked to help with awareness

The bench also asked the petitioner's side to draw up a concrete plan for how advocates can contribute to building public awareness about keeping the river clean.

The river's revival has been the subject of a public interest litigation pending before the Gwalior bench since 2019, filed by advocate Vishwajeet Ratoniya, according to earlier reports in the legal news website LiveLaw.

What happens next

The WRD, PWD, municipal corporation and the petitioner must each place their action plans and responses before the court within two weeks, after which the bench is expected to take up the matter again.