Dilip Buildcon Limited said on 23 November 2026 that it has received a Letter of Award worth Rs 901.43 crore, including Goods and Services Tax (GST), from NBCC (India) Limited for a group housing package of the planned satellite township at Rakh Gund Aksha in Bemina, on the outskirts of Srinagar in Jammu and Kashmir.

The infrastructure company disclosed the award to BSE Limited and the National Stock Exchange of India (NSE) early on Monday morning; the filing was digitally signed by Company Secretary Abhishek Shrivastava at 9:05 am.

What has Dilip Buildcon been hired to build?

Dilip Buildcon will build Package 3 (Group Housing 02), including allied works, under Phase I of the satellite township, according to the filing. The work is on an engineering, procurement and construction (EPC) basis, which means the contractor handles design, engineering, purchase of materials and construction.

The company has 24 months to complete construction. It will then operate and maintain the project for two years. The filing does not say how many housing units the package includes.

Dilip Buildcon described the contract as a general contract awarded by a domestic entity. It said its promoters have no interest in NBCC and the contract is not a related-party transaction.

What is the Bemina satellite township?

The satellite township is a large planned urban development on Srinagar's north-western edge, for which the Srinagar Development Authority (SDA) brought in NBCC, a public sector enterprise under the Union Ministry of Housing and Urban Affairs. The two signed a memorandum of understanding in August 2024.

At the time, NBCC said it would act as project management and marketing consultant for a township of about 406 acres at Rakh Gund Aksha, with an estimated cost of about Rs 15,000 crore, as reported by ThePrint from an ANI report on 9 August 2024. NBCC's plan listed residential plots, villas, apartment complexes, commercial offices, an indoor sports centre, a 200-key five-star resort and around 3,200 affordable homes, to be built in phases over five years. A local report in the Kashmir Reader that month gave the site area as about 2,950 kanals (roughly 369 acres), so the published size figures differ.

The Kashmir Reader also reported in August 2024 that the site lies next to the planned Medi City and the High Court complex, and that construction would be awarded through tenders.

Why does this order matter?

The award is a sign that the Bemina township is moving from planning into construction contracts. NBCC has said the self-sustaining model will fund the township through sales of villas, commercial space and other components, according to the same 2024 report.

For Dilip Buildcon, the filing describes a single domestic EPC contract; the company did not comment on expected margins or on how the work fits its existing order book.

What happens next?

A Letter of Award is usually followed by a formal contract agreement before work begins. The filing does not give a start date. If construction starts soon, the 24-month construction period would run to late 2028, followed by two years of maintenance. NBCC and the SDA have not, in the material reviewed by MapMyTimes, published a fresh timeline for the rest of the township.

Under its insider trading code, Dilip Buildcon said its trading window for insiders would stay closed until 48 hours after the information became public.