West Central Railway has completed 89 kilometres of track along the 111-kilometre Bhopal division section of the 276.50-kilometre Bhopal–Ramganjmandi railway line, with engineers targeting completion of the remaining 22 kilometres between Narsinghgarh and Kurawar by December 2026.
Track Progress Across Bhopal, Sehore, and Rajgarh
Running across Bhopal, Sehore, and Rajgarh districts in Madhya Pradesh into Jhalawar and Kota in Rajasthan, the Bhopal division stretch covers 12 stations and carries a divisional project outlay of roughly ₹1,255 crore.
During 2026 alone, WCR commissioned 52.50 kilometres across three sections—Shyampur–Kurawar (15 km), Biaora–Sonkatch (24.50 km), and Sonkatch–Narsinghgarh (13 km)—adding to earlier completed alignments between Nishatpura D-Cabin and Kurawar as well as Biaora, Rajgarh, and Sonkatch.
Key Project Milestones and Route Impact
- Total alignment: 276.50 km connecting Bhopal with Ramganjmandi near Kota.
- Madhya Pradesh work: 89 km completed out of 111 km in Bhopal division; 22 km Narsinghgarh–Kurawar link targeted for December 2026.
- Commissioning goal: Full corridor targeted by April 2027, cutting Bhopal–Kota rail travel by two to three hours.
Shorter Central India Rail Connectivity
Once linked end-to-end, the new broad-gauge corridor will provide direct rail access to towns such as Narsinghgarh and Kurawar, shave about 115 kilometres off the Jaipur–South India rail route via Bhopal, and relieve heavy passenger and freight traffic on existing trunk lines.