The first 500-metre underground stretch of Bhopal Metro's Orange Line Phase 2, linking Bhopal Railway Station and Pul Bogda near the Subhash Nagar depot, has missed its revised November-end completion deadline following slow excavation and technical halts.

The stretch forms part of Package BH-04, a 3.39-kilometre twin-tunnel underground alignment passing beneath the dense commercial corridor of Hamidia Road. Earlier, an initial May 31, 2026 target had already slipped before Madhya Pradesh Metro Rail Corporation Limited (MPMRCL) Managing Director S. Krishna Chaitanya set the November deadline last month.

Why Boring Slowed Near Hamidia Road

Engineering teams encountered soil and groundwater stabilization challenges flagged earlier in the year, requiring repeated stoppages for grouting and structural safety works before advancing tunnel boring machines underneath crowded buildings and arterial streets.

Meanwhile, work on a second underground segment spanning from Nadra Bus Stand to Sindhi Colony has yet to move beyond preliminary station construction and continues to face local objections over the proposed route below Berasia Road.

Extended Diversions for Old Bhopal Commuters

The slip in tunnel milestones means ongoing traffic diversions and barricading around Nadra Bus Stand, Hamidia Road, and Alpana Talkies are set to continue into early 2027, extending commute delays and commercial disruption across Old Bhopal.