The Bhopal Municipal Corporation (BMC) spent Saturday, 21 November 2026, finalising its third action-taken report on the drive against shops and businesses running from residential buildings in Bhopal, Madhya Pradesh, ahead of a Supreme Court hearing on Monday, 23 November 2026. The report was due to be submitted online on Sunday, 22 November, according to the Free Press Journal.
What will the Supreme Court hear on 23 November?
The court will review how far the civic body has gone in shutting commercial establishments that operate from properties meant for housing. At an earlier hearing on 22 September, the court had directed that establishments closed in the morning must not reopen by evening, particularly in Bhopal. The Supreme Court had also stayed proceedings of a 10-member committee set up by the Madhya Pradesh government on the issue and cancelled relief that the High Court had granted to some shop operators, Dainik Jagran reported.
On 21 November, BMC officials and building-permission engineers met at the corporation's headquarters to settle the report. Officials were also to carry an affidavit to New Delhi for the corporation's counsel and the amicus curiae, AK Sinha, the Free Press Journal reported.
How many properties has BMC sealed?
By the BMC's own figures, as reported by the Free Press Journal, the corporation has served 9,992 notices across three phases and sealed 639 properties: 101 in the first phase, 190 in the second and 348 in the third phase, which began on 16 November with 24-hour notices. Deputy Commissioner Bhuwan Gupta told the paper the drives were being carried out in line with the Supreme Court's directions.
Those numbers are small against the scale of the problem. Figures cited during the civic action put the number of establishments operating in Bhopal's residential areas at around 62,500.
Why are the figures being questioned?
- The Free Press Journal reported that some establishments closed voluntarily after proceedings were recorded, raising doubts over whether they should count as "sealed".
- The paper said areas such as Arera Colony and Rohit Nagar were left largely untouched in the third phase. A planned action in Arera Colony's E-4 sector was called off, and a demolition at an under-construction showroom near the No. 10 market was only partly completed.
- Petitioner Vivek Tripathi alleged that officials were sealing shops mainly for photographs and paperwork, and said he would raise this at the hearing, according to Dainik Jagran.
Traders' groups have pushed back too. Bhopal Vyapari Mahasangh president Anand Soni said the timing hurts businesses and customers during the wedding season, and traders argue that establishments that fit the draft Bhopal Master Plan should not face immediate action while it is under discussion.
What happens next
The 23 November hearing is expected to decide the next steps for the drive, including whether the court is satisfied with the BMC's compliance. The outcome could affect thousands of shops, clinics and offices that run from homes across the city. The corporation is also dealing with other civic pressures, including the recent contaminated-borewell scare in Ashoka Colony.