The Bhopal Municipal Corporation (BMC) has fined the private agency handling the clean-up of the Adampur landfill Rs 3.2 lakh for slow disposal of processed waste, days before the corporation is due to appear before the Supreme Court over the site on 17 November.
The penalty on Saurashtra Enviro was ordered on Saturday, 14 November, after BMC Commissioner Ramprakash Ahirwar inspected the landfill and expressed dissatisfaction with the pace of work, the Free Press Journal reported.
Processed, but not removed
Adampur holds about 6.5 lakh metric tonnes of legacy waste, according to the report. BMC says 2.5 lakh tonnes has been processed, but only about 2 lakh tonnes has actually left the site.
The gap lies in refuse-derived fuel, or RDF, the combustible fraction separated out when old garbage is processed. That material has piled up at Adampur because it has not been transported onward for disposal, leaving large parts of the landfill covered in it. The report also says more than 50 tonnes of discarded clothes have accumulated at the site, which it describes as a fire hazard.
Two contracts, one agency
Saurashtra Enviro holds a Rs 53 crore contract to remediate the legacy waste at Adampur. BMC has also given the same company a separate Rs 48 crore contract to manage the fresh waste that continues to reach the site, spending that was cleared by the mayor-in-council and the municipal council.
Five machines are currently processing the old waste. The company says it has added two more and plans to bring in a multi-deck processing machine and a roto-screen. Earlier proposals for waste-to-energy plants at the site, including a project by NTPC to convert waste into electricity, gas and charcoal, did not go ahead, the newspaper said.
Supreme Court pressure
The landfill is under the Supreme Court's watch after repeated fires at the site, which led the court to reprimand the corporation. In an affidavit, BMC has promised the court that all legacy waste will be cleared within 330 days, by 31 March 2027. The agency itself has a February deadline to dispose of the legacy waste and RDF.
BMC has named Superintending Engineer Santosh Gupta to represent it at the 17 November hearing.
Why it matters
The site's history of fires is why the court is involved, and the report flags the stockpiled textile waste as a fire hazard. The figures in the report suggest the clean-up is behind the pace needed to meet the deadline BMC itself gave the court: roughly 2 lakh of 6.5 lakh tonnes has been removed so far.
What next
The Supreme Court hearing on 17 November will be the first test of BMC's progress since its affidavit. How quickly the stockpiled RDF can be moved off-site, and whether the additional machines speed up processing, will determine whether the March 2027 target is realistic.