Kempegowda International Airport (KIA) in Bengaluru, Karnataka, began simultaneous operations on its two parallel runways on 27 November 2026, after the Directorate General of Civil Aviation (DGCA) approved the change on 3 November. Media reports say the move makes Bengaluru the second airport in India, after Delhi, to adopt the arrangement.
What changes for flights at Bengaluru airport?
Aircraft can now take off from both the northern and southern runways at the same time, subject to air traffic control clearance and safety requirements. Until now, KIA largely ran its runways in segregated mode, with one mainly handling arrivals and the other mainly handling departures. Business Today reported that the first phase focuses on simultaneous departures from both runways. Arrivals will still be assigned according to air traffic control clearances and operational needs.
How much extra capacity will it add?
According to the reports, the airport's approved handling capacity rises from about 60 aircraft movements an hour to about 85, an increase of nearly 42 per cent. Asianet Newsable reported that the current figure of 60 is made up of roughly 30 arrivals and 30 departures an hour.
The airport tested the system before the launch. During a trial on 20 November, about 40 departures and 20 arrivals were handled between noon and 1 pm, according to Asianet Newsable.
Why it matters for passengers
Bengaluru is one of India's busiest airports, and morning and evening peaks often bring departure queues and holding patterns. The reports say that letting both runways handle take-offs could cut the time aircraft spend waiting for clearance or circling before landing. That could help airlines keep to their schedules and reduce fuel burn and carbon emissions.
The benefits are expected rather than proven. The reports note that real-world gains will depend on weather, airspace restrictions, traffic volumes and ground-handling capacity, and that the new system will not remove delays caused by bad weather or congested airspace.
What is confirmed and what is not
The DGCA approval date of 3 November, the 27 November start date and the capacity figures come from news reports citing the airport's plans. MapMyTimes could not independently access a formal statement from Bangalore International Airport Limited (BIAL), the airport operator, or from the DGCA about the launch. Neither report carried direct quotes from officials or airlines.
What comes next
The runway change is part of a wider set of airfield upgrades by BIAL. According to Asianet Newsable, these include additional taxiways and aircraft parking bays, a planned western cross-taxiway to improve movement between the northern and southern runway systems, expansion of Terminal 2 under Phase 2 and a new air traffic control tower. Moving from simultaneous departures to fuller mixed use of both runways would depend on further operational clearances, which the reports did not detail.
Elsewhere in the region, the Defence Ministry is expanding infrastructure at Bengaluru's Yelahanka Air Base ahead of Aero India 2027. In Maharashtra, Navi Mumbai International Airport recently crossed four million passengers, a sign of the wider pressure on India's airport capacity.